PROJECT 01 / RENEWABLE ENERGY / ZAMBIA

Kanakantapa
Solar + Storage.

Chongwe District · Lusaka Province, Zambia

Phase 1 combines solar generation connected to the grid with battery storage in Chongwe, alongside Zambia’s Lusaka demand centre.

Fully fundedContract finalisation & mobilisation
9 MWAC generation capacity
10.8 MWpDC solar capacity
2 MWhBattery energy storage
25 yearsUSD PPA term in the brief
ChongweLusaka Province, Zambia

THE ASSET & ITS LOCATION

Solar generation.
Solar generation with battery storage.

Phase 1 is a 9 MW AC / 10.8 MWp DC solar installation with a 2 MWh battery, developed as the first operating asset on a site planned for 30 MW AC.

The site is in Chongwe District, Lusaka Province, near the Lusaka demand centre and the Chongwe / Leopards Hill grid corridor. The project overview describes secured land, access arrangements and a phased layout for the full development.

21,760 MWhModelled first year output · P50
19,584 MWhModelled first year output · P90

Generation estimates are September 2026 model outputs, rather than measured operating results. P50 is the central estimate; P90 is the more conservative case.

Kanakantapa site terrain photographed in the supplied project overview
The Kanakantapa site.Actual site photograph from the project overview.

FROM CAPITAL TO DELIVERY

Funding complete.
The next chapter is execution.

The current focus is contract finalisation and mobilisation. Construction, commissioning and operation follow through the delivery programme.

  1. COMPLETE

    Funding

    Phase 1 is fully funded, with funding completion at 100%.

  2. CURRENT PHASE

    Contract finalisation

    Finalising the remaining contractual documentation and responsibilities for delivery.

  3. CURRENT PHASE

    Mobilisation

    Preparing the team, site logistics and implementation arrangements for the construction phase.

  4. NEXT MILESTONE

    Construction

    The project brief anticipates a build lasting 10 to 12 months. The final implementation programme will define milestone dates.

  5. TARGET

    Commissioning

    January 2028 is the commercial operation target stated in the September brief, subject to the final delivery programme.

CURRENT TRACKING FOCUS

Documentation. Readiness. Milestones.

The next dashboard updates will record contract and mobilisation milestones as they are confirmed.

PHASE 1

Project funding.

Phase 1 has reached full funding and is in contract finalisation and mobilisation.

US$8.8m project cost

Estimated cost for Phase 1, including solar generation and battery storage.

100% funded

Funding status was reported on 13 October 2026. Construction milestones are tracked separately.

FUTURE PHASES

A first asset.
A larger development pathway.

The site is planned for development in phases.

9 MW ACCurrent Phase 1
30 MW ACPlanned full site

The full site plan pairs 30 MW AC with 7.5 MWh of storage, delivered in phases from 2028 onward.

The 100% funding status shown on this dashboard applies to the current Phase 1. Expansion capacity is a development plan, with its own financing and execution requirements.

FOLLOW THE NEXT MILESTONE

From a funded project
to a delivered asset.

Kanakantapa’s next updates will focus on contract finalisation, mobilisation and the construction programme.